Town centre level crossing to close for £215,000 upgrade
Closures at a town centre level crossing will be imposed while a £215,000 upgrade is being carried out.
Motorists and pedestrians are being urged to check their journeys before setting off while works to improve rail reliability and safety at the Winsover Road crossing in Spalding go on, Network Rail has warned.
The crossing will be closed during these times: Saturday, July 5 from 8.30pm to Monday, July 7 at 7am; Saturday, July 12 from 8.30pm to Monday, July 14 at 7am; Monday, August 11 from 9.30pm to Tuesday, August 12 at 6.30am; Tuesday, August 12 from 9.30pm to Wednesday, August 13 at 6.30am.
The comprehensive renovation will replace the life-expired crossing surface, deck units, cill beams (the interface between tarmac and railway), tarmac and road markings.
By scheduling the work when no trains are running, these essential improvements can be completed with the least possible disruption to passenger journeys and local residents.
Matthew Story, works delivery supervisor for Network Rail, said: "This significant investment will deliver a much smoother and safer crossing for both rail and road users.
“We understand the disruption this essential work may cause and thank the local community for their patience while we complete these important upgrades.
"The current crossing surface has reached the end of its operational life and requires replacement to ensure continued safety and reliability.
“We've scheduled much of the work overnight and during weekends to minimise disruption to the public."
Road diversion routes will be in place and clearly signposted throughout the closure periods.