New pictures show the progress which is being made on creating a new A16 roundabout.

Lincolnshire County Council is increasing the size of the A16/B1180 Greencell roundabout at Pinchbeck in order to provide two wider lanes thanks to a £20million Levelling Up grant.

Work has been taking place for several months now, which included an eight-week closure in the summer, and the changes are starting to take shape.

A fourth arm has been added to the Greencell roundabout as part of the A16 improvement works
A fourth arm has been added to the Greencell roundabout as part of the A16 improvement works

Highways officials have confirmed that the roundabout has been ‘future proofed’ by adding a fourth arm - should the land near Vernatt’s Drain be developed.

Changes to this roundabout is part of a wider scheme which also sees improvements to the Springfields roundabout and Marsh Lane, Boston.

The Greencell roundabout for the A16 project - which is estimated to cost £6.6million - started earlier this year and is set to finish in spring 2025.

Progress is being made on the Greencell roundabout in Pinchbeck
Progress is being made on the Greencell roundabout in Pinchbeck