From Sutton Bridge to Bicker Fen for massive transformer
A transformer weighing as much as 34 African elephants made its way from the port at Sutton Bridge to Bicker Fen this morning.
The transformer, which is longer than two red London buses had arrived at the port from Austria, where it was made.
It was lifted onto a trailer and driven, by police escort, 20 miles to the Triton Knoll onshore substation site.
There will be another delivery next Sunday and, once the transformers are skidded into position, the installation of associated electrical equipment will begin. As this is the most important equipment on site, this marks a significant milestone in the project.
Transformers change the voltage of the power delivered to the onshore substation so it can be delivered to the National Grid and transmitted to homes and businesses
Once the other associated electrical equipment has been added, each transformer will be 26 metres long and 6.6 metres wide, and weigh a whopping 240 tonnes.
The transformer forms the backbone of modern energy grids, and its reliable operation is crucial to ensuring a stable and resilient power supply. They change voltage of the power which comes down the offshore cable, so it can be pushed into the grid and to people’s homes and businesses.
The wind farm, 32km off the Lincolnshire coast, will have an installed generation capacity of circa 857MW once fully operational. It will be capable of providing enough clean and sustainable power for the equivalent of at least 800,000 UK homes, making a significant contribution to the UK’s renewable energy targets.
There are around 150 people on site at Bicker Fen. The substation construction work has progressed significantly over the last year, with works including the construction of the main access road, the substation platform, piling works and access to the existing National Grid substation already completed, while civils works started earlier this year and are well developed. Construction of the onshore substation is due to be completed in 2020.
Phil Manley, Triton Knoll project director, of Siemens Transmission and Distribution, said: “The transformers are one of the most important parts of the onshore substation site. Without the transformer, the power generated by the offshore wind farm would not be able to be transmitted into the grid. I’m delighted that we’ve reached this stage according to the project schedule.”
Julian Garnsey, project director for Triton Knoll and innogy, said: “This is a significant milestone in the construction of the Triton Knoll onshore substation, which sits at the very heart of our project. We’ve made major progress in the last year, with the substation platform, foundations and infrastructure taking real shape on site. We’re now preparing to start offshore construction in the first quarter of 2020, so the installation of this impressive equipment ensures we stay on track to become a major UK state-of-the-art renewable energy generator, typically powering over 800,000 UK homes.”